Milestone Payment Based Multi-mode Multi-project Cash Flow Balance Scheduling Optimization
HE Yukang, JIA Tao, WANG Nengmin
1. School of Management, Xi’an Jiaotong University, Xi’an 710049, China; 2. The Key Lab of the Ministry of Education for Process Management & Efficiency Engineering, Xi’an 710049, China
HE Yukang, JIA Tao, WANG Nengmin. Milestone Payment Based Multi-mode Multi-project Cash Flow Balance Scheduling Optimization[J]. Operations Research and Management Science, 2023, 32(8): 38-43.
[1]LEYMAN P, VANHOUCKE M. Capital- and resource-constrained project scheduling with net present value optimization[J]. European Journal of Operational Research, 2017, 256: 757-776. [2] 崔南方,梁洋洋,赵雁.考虑鲁棒性的Max-npv项目调度问题[J].系统工程理论与实践,2016,36(6):1462-1471. [3] FATHI H, AFSHAR A. GA-based multi-objective optimization of finance-based construction project scheduling[J]. KSCE Journal of Civil Engineering, 2010, 14: 627-638. [4] 郑维博,何正文,刘人境.基于融资能力约束的多模式Max-npv项目调度优化:双重视角[J].运筹与管理,2016,25(1):25-34. [5] Al-SHIHABI S T, ALDURGAM M M. A max-min ant system for the finance-based scheduling problem[J]. Computers and Industrial Engineering, 2017, 110: 264-276. [6] ELAZOUNI A. Heuristic method for multi-project finance-based scheduling[J]. Construction Management and Economics, 2009, 27: 199-211. [7] LIU S S, WANG C J. Profit optimization for multiproject scheduling problems considering cash flow[J]. Journal of Construction Engineering and Management, 2010, 136: 268-1278. [8] El-ABBASY M S, ELAZOUNI A, ASCE T Z F. Generic scheduling optimization model for multiple construction projects[J]. Journal of Computing in Civil Engineering, 2017, 31: 04017003. [9] 于懿宁,徐哲,刘东宁.考虑多技能人力资源的分布式多项目调度问题[J].系统工程理论与实践,2020,40(11):2921-2933. [10] 张静文,刘婉君,李琦.基于关键链改进搜索的遗传算法求解分布式多项目调度[J].运筹与管理,2021,30(3):123-129. [11] HE Z W, HE H, LIU R J, et al. Variable neighbourhood search and tabu search for a discrete time/cost trade-off problem to minimize the maximal cash flow gap[J]. Computers & Operation Research, 2017, 78: 564-577. [12] 宁敏静,郑小强,何正文.基于随机活动工期的现金流动态均衡前摄性与反应性项目调度优化[J].运筹与管理,2021,30(2):117-123. [13] HE Y K, HE Z W, WANG N M. Tabu search and simulated annealing for resource-constrained multi-project scheduling to minimize maximal cash flow gap[J]. Journal of Industrial & Management Optimization, 2021, 17(5): 2451-2474.