Research on Portfolio Selection with Divisibility under the Influence of Precedence Relationship
ZHANG Junxia, LI Xingmei, SHEN Zhong, XU Chuanbo
1. School of Economics and Management, North China Electric Power University, Beijing 102206, China; 2. Beijing Key Laboratory of New Energy and Low-carbon Development, Beijing 102206, China
ZHANG Junxia, LI Xingmei, SHEN Zhong, XU Chuanbo. Research on Portfolio Selection with Divisibility under the Influence of Precedence Relationship[J]. Operations Research and Management Science, 2024, 33(11): 160-167.
[1] 闫庆友,王雅娴,孙艺新.动态主动打断项目组合选择问题的模型研究[J].运筹与管理,2020,29(8):158-166. [2] 李星梅,王丽,赵秋红.受融资影响的项目组合选择研究[J].运筹与管理,2022,31(1):176-182. [3] 马绍益,李星梅,李金孟.受弹性时间段和价值波动双重影响的项目组合选择问题研究[J].中国管理科学,2021,29(8):106-115. [4] BAI L B, HAN X, WANG H L, et al. A method of network robustness under strategic goals for project portfolio selection[J]. Computers and Industrial Engineering, 2021, 161: 107658. [5] LORIE J H, SAVAGE L J. Three problems in rationing capital[J]. The Journal of Business, 1955, 28(4): 229-339. [6] TERRY R A, THOMAS G P, JACK M. An analysis of risk sharing in strategic R&D and new product development projects[J]. International Journal of Project Management, 2016, 34(6): 914-922. [7] 李星梅,王雅娴,赵秋红.兼顾企业风险态度的主动打断项目组合选择风险研究[J].管理工程学报,2019,33(2):188-195. [8] DELERUE H, SICOTTE H. Resource interdependence and project termination: An analysis in the biopharmace-utical industry[J]. International Journal of ProjectManagement, 2020, 35(5): 256-266. [9] GOUBAA A, KHAlGUI M, LI Z, et al. Scheduling periodic and aperiodic tasks with time, energy harvesting and precedence constraints on multi-core systems[J]. Computers Netwoks & Communications, 2020, 520(3): 86-104. [10] 李星梅,王雅娴,赵秋红.考虑多因素的可打断项目组合选择模型研究[J].运筹与管理,2018,27(4):144-152. [11] SERVAKH V V, SUKHIKH S L. Hybrid algorithm for scheduling with regard for reinvestment of profits[J]. Automation & Remote Control, 2004, 65(3): 449-455. [12] BELENKY A S. A Boolean programming problem of choosing an optimal portfolio of projects and optimal schedules for them by reinvesting within the portfolio the profit from project implementation[J]. Applied Mathematcis Letters, 2012, 25(10): 1279-1284. [13] LI X M, FANG S C, TIAN Y, et al. Expanded model of the project portfolio selection problem with divisibility, time profifile factors and cardinality constraints[J]. Journal of the Operationa Research Society, 2015, 66(7): 1132-1139. [14] 李移山.探讨监理企业运用CM模式参与PPP项目管理的可行性研究[J].建设监理,2020(10):9-12. [15] LI X M, FANG S C, GUO X L, et al. An extended model for project portfolio selection with project divisibility and interdependency[J]. Journal of Systems Science & Systems Engineering, 2016, 25(1): 119-138. [16] 李星梅,钟志鸣,赵秋红.求解多项目组合选择问题的奔德斯分解算法[J].系统工程理论与实践,2018,38(11):2863-2873. [17] STUMMER C, HEIDENBERGER K. Interactive R&D portfolio analysis with project interdependencies and time profiles of multiple objectives[J]. IEEE Transactions on Engineering Management, 2003, 50(2): 175-183. [18] HAJDU M. Survey of precedence relationships: Classification and algorithms[J]. Automation in Construction, 2018, 95: 245-259.