运筹与管理 ›› 2015, Vol. 24 ›› Issue (6): 143-151.DOI: 10.12005/orms.2015.0206

• 应用研究 • 上一篇    下一篇

施工项目中设计风险元传递模型研究

李存斌, 刘赟奇, 李书科   

  1. 华北电力大学 经济与管理学院,北京 102206
  • 收稿日期:2014-10-10 出版日期:2015-12-25
  • 作者简介:李存斌(1959-),男,硕士,教授,博士生导师,研究方向:信息管理、项目风险管理;刘赟奇(1979-),男,博士研究生,研究方向:项目管理、风险管理;李书科(1978-),女,博士研究生,研究方向:风险管理、信息管理。
  • 基金资助:
    国家自然科学基金资助项目(71271084,71071054);中央高校基本科研业务费专项资金资助(2014XS55,2015XS32);北京市产学研联合培养研究生基地项目

Study on Model of Design Risk Element Transmission in the Construction Project

LI Cun-bin, LIU Yun-qi, LI Shu-ke   

  1. School of Economics and Management, North China Electric Power University, Beijing 102206, China
  • Received:2014-10-10 Online:2015-12-25

摘要: 针对设计变更对项目实施的影响,本文将影响施工项目的设计变更原因称为项目的设计风险元,基于广义项目风险元传递理论建立系统动力学模型,动态研究设计风险元传递过程。通过模型模拟分析不同时间、不同程度的设计风险元对项目工期和项目费用影响程度,当设计风险元发生后,设计审批及设计过程将影响项目工期;受施工工序影响设计风险元造成实际施工速度不饱和,使得施工效率低下形成窝工;由于设计风险元导致的返工造成施工项目的工期延误和成本超支。此模型为风险管理者或项目管理者在设计风险管理方面提供了有力依据。

关键词: 项目管理, 设计风险, 风险元传递, 系统动力学

Abstract: Design risk is one of the main reasons for leading to rework in the process of the construction. In this paper, based on the generic project risk element transmission theory and system dynamics, a system dynamics model of construction project design risk element transmission is developed. The factors leading to the quantity increase of construction projects are considered as design risk element, and after the analysis of transfer process of design risk element in construction project, a corresponding causal feedback loop is constructed. By assigning values to model variables and establishing functions between them, the model is simulated through software Vensim. The results indicate that design risk element exerts different degree of influence on project cost and time, and that the more design risk element occurs or the later design risk element occurs, the faster will the impact accelerate through the internal structure of project. In addition, it can be concluded that the model results chart, which reflects the dynamic changes of individual construction project, can provide sound evidence for risk management and project management.

Key words: project management, design risk, risk element transmission, system dynamics