Operations Research and Management Science ›› 2013, Vol. 22 ›› Issue (3): 36-44.

• Theory Analysis and Methodology Study • Previous Articles     Next Articles

Study on Optimization and Simulation of DSM Project Schedule Based on Activities Overlapping

ZHANG Chun-sheng, YAN Guang-le   

  1. College of Management, University of Shanghai for Science and Technology, Shanghai 200093, China
  • Received:2011-04-21 Online:2013-06-25

基于活动重叠的DSM项目进度优化与仿真

张春生, 严广乐   

  1. 上海理工大学 管理学院,上海 200093
  • 作者简介:张春生(1972-),男,河北高阳人,博士研究生,研究方向:复杂系统,项目管理;严广乐(1957-),男,广东南海人,教授、博士生导师,博士,研究方向:管理科学与工程。
  • 基金资助:
    上海市研究生教育创新计划资助;上海市一流学科建设资助项目(S1201YLXK)

Abstract: Overlapping between project activities can shorten project schedule, but it can result in a rework risk. Therefore, the paper first adopts the design structure matrix(DSM), proposes activities advancing overlapping factor DSM and activities crashing overlapping factor DSM, combines rework risk DSM, aiming to completely describe the effect of activities overlapping on rework. Finally, the author presents a hybrid particle swarm algorithm for schedule optimization based on activities overlapping. The calculation proves that the method can not only reduce the duration of projects, but also provide decision-makers with a new perspective in properly choosing activities overlapping.

Key words: project management, activities overlapping, design structure matrix, schedule optimization, particle swarm optimization(PSO)

摘要: 项目活动之间的重叠虽然可以缩短项目工期,但又存在返工风险。为此,本文采用设计结构矩阵(DSM),提出活动超前重叠因子矩阵和活动赶工重叠因子矩阵,结合返工风险矩阵,完整地描述了项目活动的重叠及其对返工的影响。提出了基于活动重叠的混合粒子群项目进度优化方法。通过案例计算表明,该法可以有效缩短项目工期,同时为项目决策者合理选择活动重叠量提供了新思路。

关键词: 项目管理, 活动重叠, 设计结构矩阵, 进度优化, 粒子群优化