关键链断裂情况下的缓冲设置方法比较研究

崔南方1,赵雁2,胡雪君1,田文迪3   

  1. 1.华中科技大学 管理学院,湖北 武汉 430074;
    2.中南财经政法大学 工商管理学院,湖北 武汉 430073;
    3.武汉纺织大学 管理学院,湖北 武汉 430073
  • 收稿日期:2013-03-14 出版日期:2016-06-25
  • 作者简介:崔南方(1963-),男,江西宁都人,教授,博士生导师,研究方向:项目调度,供应链管理;赵雁(1984-),女,山东烟台人,通讯作者、讲师,研究方向:项目管理,鲁棒性项目调度;胡雪君(1989-),女,湖北襄阳人,博士,研究方向:项目调度,关键链项目管理;田文迪 (1984-), 女, 湖北罗田人,讲师,博士,研究方向:项目调度,项目管理。
  • 基金资助:
    国家自然科学基金资助项目(71271097,71201119);中央高校基本科研业务青年教师资助项目(31541410812)

Comparative Research on Buffer Management for Critical Chain Gaps

CUI Nan-fang1, ZHAO Yan2, HU Xue-jun1, TIAN Wen-di3   

  1. 1.School of Management, Huazhong University of Science and Technology, Wuhan 430074, China;
    3.School of Management, Wuhan Textile University, Wuhan 430073, China;
    2.School of Business Aaministration, Zhongnan University of Economics and Law, Wuhan 430073, China
  • Received:2013-03-14 Online:2016-06-25

摘要: 应用关键链项目管理方法时,由于项目的复杂性,在确定关键链和非关键链后,进一步插入汇入缓冲时,常常会出现资源再次冲突,需要对计划进行重排,重排后又出现关键链断裂、汇入缓冲起不到保护作用等问题。针对这些问题,本文采用分散缓冲法制定项目调度计划,并用项目实例证明了方法的可行性和通用性,且设计仿真实验将分散缓冲计划与重排后的关键链调度计划进行比较,结果发现当项目活动时间的变化性较小时,应用分散缓冲法还可以获得较好的项目绩效。

关键词: 项目管理, 关键链, 分散缓冲, 集中缓冲

Abstract: In the application of critical chain buffer management, when the critical chain and non-critical chains are identified, some resource conflictions emerge again because of the complexity of project, which is to be solved by rescheduling. After rescheduling some new problems emerge, gaps may be created in the critical chain and some feeding buffers appear unavailable for protection. This paper aims to set up a project plan by the scattered buffers method to avoid those problems. And project examples are used to prove the feasibility and universality of this method. Furthermore, simulation experiments are designed to compare the scattered buffered plan with rescheduled critical chain plan. The results of the experiments show that scattered buffered plans perform better in the projects with small activity duration variability.

Key words: project management, critical chain, scattered buffer, centralized buffer